gurus

i have acivated inprocess inspection 03

and in routing inpection charecter is assigned

in this case we want to enter UD value after result entry

pls clarify

Faisal

Accepted Solutions (1)

Accepted Solutions (1)

kaushik_choudhury2
Active Contributor
0 Kudos

Hello Faisal,

Where and what issue you are facing to record the result and UD ?

Cheers

Kaushik

muhamed_faisal
Active Participant
0 Kudos

Hi

My dout is that after entering the result

wether ud is must to close this inpection lot

as there is not sock movement is happening

Faisal

kaushik_choudhury2
Active Contributor
0 Kudos

Hello Faisal,

In the configuration of the 'Parameters for order confirmation ' (OPK4) under QM result recoding we can maintain the system behavior if the QM inspection results are not recorded . Also check the Operation sequence field in the same tab.

I hope the information helps

Cheers

Kaushik

Former Member
0 Kudos

As I understand there is no connection between 03 & 04 (which is confirmation of order/close )

What I means is as 03 inspection type is not stock relevant ,even if you do not take UD of this lot it will allow to do successive processes.

Also Even if you do not do result recording still you can directly take UD.

Answers (0)