Hi,
I have a operative project with budget profile having overall budget and availability contril is active. There is cost booking exist for the entire last year.
Now i want to change my assign Annualy type budget profile by removing existing Overall type.
Can anyone tell me the impact and limitations for the said change ? and what will be the correct procedure to do the same.
regards,
issue is resolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I dont think any major precautionary steps required, only thing would be your last year assigned values should be given as budget for last year, the overall budget minus this value will be spread out to the remaining year.
Use CJBW, deactivate the availability control.
With OPSX reset the budget status.
Do all the required changes.when you do annual budgeting, the status will again become budgeted.
If availability control is not active, activate it by CJBV.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.