Dear Experts,
Just want to ask how PurRqs Planned dates in MD04 is calculated compared to Availability /Reqmnts Date in RRP3 in APO.
Below are the examples:
In APO RRP3 we have (PurRqs A) = Start date 6/21/2011, Avail / Reqmts Date 7/01/2011
In R/3 MD04 we have the same (PurRqs A) -> Planned dates = 7/02/2011, Delivery date = 6/22/2011, Release date = 6/21/2011, GR pr time = 9
In APO RRP3 we have (PurRqs B) = Start date 7/22/2011, Avail / Reqmts Date 8/01/2011
In R/3 MD04 we have the same (PurRqs B)= Planned dates = 8/03/2011, Delivery date = 7/23/2011, Release date = 7/22/2011, GR pr time = 9
Thanks in advance,
Marcus
Marcus,
The short answer: 'it depends'.
Read the online help about date comparisons between R/3 and APO
http://help.sap.com/saphelp_scm70/helpdata/EN/98/763442d692ac04e10000000a1550b0/frameset.htm
There are also a bunch of OSS notes on the subject. Start with
https://service.sap.com/sap/support/notes/333386
For STOs/STPrqs
https://service.sap.com/sap/support/notes/1342195
https://service.sap.com/sap/support/notes/361308
and many more.
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.