Dear Experts,
Just want to ask how PurRqs Planned dates in MD04 is calculated compared to Availability /Reqmnts Date in RRP3 in APO.
Below are the examples:
In APO RRP3 we have (PurRqs A) = Start date 6/21/2011, Avail / Reqmts Date 7/01/2011
In R/3 MD04 we have the same (PurRqs A) -> Planned dates = 7/02/2011, Delivery date = 6/22/2011, Release date = 6/21/2011, GR pr time = 9
In APO RRP3 we have (PurRqs B) = Start date 7/22/2011, Avail / Reqmts Date 8/01/2011
In R/3 MD04 we have the same (PurRqs B)= Planned dates = 8/03/2011, Delivery date = 7/23/2011, Release date = 7/22/2011, GR pr time = 9
Thanks in advance,
Marcus
Hi Marcus,
Your datau2019s are not enough to compare........check below points
1) APO side - planned del time , GR/GI time, transport duration in T lane
2) corresponding R/3 settings? schedule margin key settings , planned del time opening date..etc
3)time zones of user In APO and R/3 ?
4) if its manually created location , products in APO ..then compare with R/3 ... make sure all are same
5)planned order originally created in APO and moved to R/3 or Created in R/3 and CIFed to APO.
give some of above info so that we can compare..... it seems some issues in your settings....
Regards
Thennarasu.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Marcus,
There are some consulting notes that explain why there is difference in the purchase orders dates between the system.
The most relevant is note 333386.
The best regards,
Michel Bohn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.