How PurRqs Planned dates in MD04 is calculated compared to PurRqs in APO

Former Member
0 Kudos

Dear Experts,

Just want to ask how PurRqs Planned dates in MD04 is calculated compared to Availability /Reqmnts Date in RRP3 in APO.

Below are the examples:

In APO RRP3 we have (PurRqs A) = Start date 6/21/2011, Avail / Reqmts Date 7/01/2011

In R/3 MD04 we have the same (PurRqs A) -> Planned dates = 7/02/2011, Delivery date = 6/22/2011, Release date = 6/21/2011, GR pr time = 9

In APO RRP3 we have (PurRqs B) = Start date 7/22/2011, Avail / Reqmts Date 8/01/2011

In R/3 MD04 we have the same (PurRqs B)= Planned dates = 8/03/2011, Delivery date = 7/23/2011, Release date = 7/22/2011, GR pr time = 9

Thanks in advance,

Marcus

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Marcus,

Your datau2019s are not enough to compare........check below points

1) APO side - planned del time , GR/GI time, transport duration in T lane

2) corresponding R/3 settings? schedule margin key settings , planned del time opening date..etc

3)time zones of user In APO and R/3 ?

4) if its manually created location , products in APO ..then compare with R/3 ... make sure all are same

5)planned order originally created in APO and moved to R/3 or Created in R/3 and CIFed to APO.

give some of above info so that we can compare..... it seems some issues in your settings....

Regards

Thennarasu.M

former_member492024
Active Participant
0 Kudos

Hello Marcus,

There are some consulting notes that explain why there is difference in the purchase orders dates between the system.

The most relevant is note 333386.

The best regards,

Michel Bohn