What is the concept of automatic User decision concept in QM
If i want to bring this concept what are the setting required
Please give me a detail answer
Thanks in advance
Faisal
The concept of Auto UD is
When you do not want manually go to QA32/QA11 & to carry out Usage decision every time ,then you can make setting for "Auto Usage Decision"
I QM view inspection type there is provision of "Auto UD" & "SKip"
Generally AUto UD is done for the lot
1.for which result recording done & all char has status 5-->closed & completed.
2.All char as "Skipped'
for auto UD to set in background you need to
1.for this plz. check in spro>Quality Management>Basic Settings>Maintain Settings at Plant Level>select plant>inslot completion>automatic usage decision --> Enter delay time for skip lot.
2.In QA16 create the variant & in QA17 run the variant with schedule.
or
2.Use QA10 & make variant & Run Variant through SM37
I hope this will help
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.