on 05-04-2011 12:16 PM
Hi
When we run settlement CJ88 or CJ8g it is not picking up all the costs to settle from WBS to Profitability Segment. The costs could be time or other costs, the network activity where the costs originate settle intially using a FUL settlement type to WBS element correctly and are settled within the same period, but in some instances when we then try and settle these costs and revenues to the PSG from the WBS element they are not recognised by the settlement run to settle. The settlement rule on the WBS is settlement type PER. I have checked the cost element and profit master data and these are all active and correct.
We are getting no errors and no other information to try and understand why this is occuring.
Please let me know if anyone else has had this issue and how it was solved.
thanks
PS all costs and settlements are in the same period.
following are the reasons which I can see
-- cost element not part of source
-- settlement might have been happened , check previous settlment
-- settlement not correct , first do it for network & then do it for project with hierarchy selection
-- cost is not part of settlement period
-- check PA structure for incompleteness
--
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
We are not using source structures, It seems strange that this issue is only happening in some instances, I have examples where the settlement is working correctly for the same projects using the same profiles etc. I am wondering if there is anything on the WBS Master data in CJ20n that I am missing, or if there is a system status that affects settlement. Like I said we are not getting an error it just states there is nothing to settle.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Cross check the "Source Structure" configuration (Tcode "OPKT") which is assigned to your settlment profile.
all the required cost & revenue elements must be assigned to the source structure via a cost element group.
as of now, your source structure might not be complete to match your requirement.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.