cancel
Showing results for 
Search instead for 
Did you mean: 

Budget tranfer between two projects

Former Member
0 Kudos

Hi Experts,

How to Trasfer the budget between two projects ( project A to Project B). Iam using CJ34 but it was throwing a Error"Overall budget is less than the overall release".

In current process: we are maintaing project budget in the root level wbs element. Using CJ30 assinging budet and CJ32 to release and to activate AVAC.

Could somebody guide is SAP have any other T-codes to to transfer Budget cost from one project to other.

Regards,

Peter.

Accepted Solutions (0)

Answers (4)

Answers (4)

ashutosh_saraf
Participant
0 Kudos

Use T-code KB11N to transfer cost from source to destination.Check out the option of WBS SCRn variant.

former_member230675
Active Contributor
0 Kudos

astosh..

the thread is talking about the budget transfer not actual cost.

you can not transfer budget through KB11N.

tnx,

abdul

Former Member
0 Kudos

This message was moderated.

pradeep_mahamuni
Contributor
0 Kudos

Hi,

You are transfering budget from Project A to Project B.

In project A suppoe you have budget of 1000 and it ie released for the full amount 1000.

Now you want to transfer 200 from this project A to Project B.

You have to unrelease this amont from project A. for this go to CJ32 and reduce the relsed amont by 200 and enter 800.

Now you have 200 in unrelesed stage in project A

Now system will allow you transfer the unrelesed amount from project A to project B.

Systgem always allow only the amount which is not release for budget transfer and Budget return. You can not trnsfer / return the release amonut.

regards,

Former Member
0 Kudos

Hi Peter,

The amount which you passed (in CJ34) would be less than the release amount (in CJ32) for the sender WBS element.

So, you need to release the deserved amount for the sender WBS amount in CJ32 in order carry out the transfer sucessfully.

Best Regards,

Punith.