Sales Order- scheduling delivery date for Procurment type F

Former Member
0 Kudos

Hi Expert,

In material Master , in MRP 2 View mailtained data as 1. Procurment type- F, Plant Storage Loc- 1140, In-House Production- 21 days, GR - Processing time-1 days. But while creating sales order for this material it shows only one day difference in sheduling delivery date.

Thanks in advance.

Manoj

Accepted Solutions (1)

Accepted Solutions (1)

jpfriends079
Active Contributor
0 Kudos

Hello

Procurement type F is for external production indicator

If you want to see a change in schedule accordingly, then maintain Planned Deliv. Time.

As per SAP, Planned Delivery Time in Days is Number of calendar days needed to obtain the material or service if it is procured externally. If you have different vendors for a material, you must specify an average value. The same applies if you order the material from a fixed vendor that has varying delivery times.

Or in sales doc type, maintain Lead time in days, this specify the number of days after the current date that the proposal for the requested delivery date in the sales document should be.

FYI - GR Processing Time, Goods Receipt Processing Time in Days is number of workdays required after receiving the material for inspection and placement into storage.

Thanks & Regards

JP

Former Member
0 Kudos

Thanks Jp ,

After maintaining plna delivery time Problem solved but after saving it shows on that date only in schedule line. I need to maintained any other field.

Manoj