Dear All
Can system calculate Total float and free float in hours? System is calculating in days and critical path is dependent on that.
Thanks
Atif
Hi Atif,
Float representation is always in Days in SAP.
If you need to convert it to hours, you'll have to do it out side the system (Days X no. of work hours per day ).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Asharif,
In Std SAP, Activity Floats always calculated in "Days".
Vemula