Hi,

What could be the reason for such a situation mentioned below

For a given product for a given qty, using same PPM order created for different dates ( three consecutive date ) the order execution times are different ( end time - start time) in SAP APO PP/DS.

On further investigation following is found.

The difference in execution time is because the system is considering down time operation for scheduling in some orders and not in others. Still do not know the reason why?

Regards,

Vineet

Edited by: Vineet Govind on May 2, 2011 7:54 PM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please check following points.

1. Have you defined downtimes for resource.

2. Are you using shifts and breaks which has different interval based capacity

3. Which Scheduling strategy is used for scheduling these orders as if you check the box schedule during non working time in scheduling strategy it will schedule the activity during non working times

4. Also check factory calender are there any holidays defined during this period.

Regards,

Santosh