PM Order method of work completed duration calculation

Keshi1
Active Participant
0 Kudos

Hi

Please advice how to configure the PM order work completion duration calculation.

I need to calculate the work completed hours based on the user status.

Not based on the Order status ( TECHO). It User status = TECHO order work completed hours should be calculated.

Please advice how to do this..

Regards

Kesharika

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

Hi

if you want to calculate the time using user status yo have to create the Z report which will fetch the when the user status has activated ,consult with you technical team on this

regards

thyagarjan