Hi,

There is a product master in PLANT1 w/o accounting view which has got CIFFed

APO has generated STR's from PLANT1 to PLANT2 and in APO, we are able to see the VMI TLB SO for the same and the same SO is also seen in R/3. But the STR's are not updating in R/3

Can the unmaintenance of Accounting view in R/3 for the product in PLANT 1 stop the purchase req's from getting updated to R/3 or is it something else. If the accounting view is the reason from the Stock transfer perpective, then it should have not even CIFF'ed the product master to APO...........correct my understanding

(PLANT 1 has proc type E and PLANT 2 has F with subcontracting)

Thanks,

SS

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello

Try creating a STR for this poduct in R3 and convert it to STO in R3 itself, if it works you need to check with other CIF transfer details. If it doesnt correct the R3 master data.

Regards

Deven

Former Member
0 Kudos

Hi SS,

Hope you have the active integration model for the PRs. Also check if you have maintained the publication entries (distribution entries).

Regards

Manotosh

Former Member
0 Kudos

My qustion is answered.

If there is no ACCOUTING View maintained for teh SKU in R3, then the PR generated in APO will not go to R3 as it cannot be excuted or converted to PO w/o an accouting view

Regards,

SS

Former Member
0 Kudos

Thanks