on 04-28-2011 3:33 PM
Hi All,
We have a Backorder scenario. We want it to run with Scheduling Agreemnt. Now when we create a Scheduling Agreement, it confirms the quantity though there are no quantities for that plant hence we cant run BO for that material and plant. Any suggestions how we can stop the ATP to do a check so all Sch Ag go in Not Confirmed mode and then we can run a BO.
rgds..
Ameet
Do you mean, in resheduling jobs V_V2 you want to restrict schedueling agreements for confimration.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.