cancel
Showing results for 
Search instead for 
Did you mean: 

How to make Purchase Requisition fall 1 month earlier from the PIR

Former Member
0 Kudos

Dear Experts,

We have PIR on Monthly buckets.

Is it possible to set the creation of PurRqs 1 month earlier than the PIR?

Let say the PIR is from the month of June after running locations heuristic the PurRqs should be created on the first day of May.

Thanks in advance,

Marcus

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Try with Monthly lot size and check results are as per your need.

Settings in product master:

Lot Size procedure : By period

Period type: Monthly M

No of periods as required in your case

Under scheduling in qty / date determination tab page of product master

select use period check box and enter period factor as 0.

Thanks,

nandha

Former Member
0 Kudos

Hi Nandha,

Thanks for your suggestion but Lot size per period is grouping the demands.

What we want is every PIR's will have PurRqs created 1 month in advance.

For example June PIR will have PurRqs on May, July PIR will have PurRqs on June, August PIR will have PurRqs on July, Sept PIR will have PurRqs on Aug, and so on....

Do you have any other options or ideas how to achieve this?

Thanks in advance,

Marcus

Former Member
0 Kudos

HI Marcus

You could use safety stock strategy SZ and put the number of days as 30. This would ensure that 30 days of demand will be consolidated and planned today.

Or, if you can play around with transportation duration, if you maintain transportation duration or planned delivery time (depending upon what are you using), you can maintain there as 30 days. This will ensure that all your Preqs are generated one month in advance.

Let us know if any of the above helps.

Rgds, Sandeep

Former Member
0 Kudos

Hi Sandeep,

Thanks but this is currently the setting we have done.

We set it to 30 days supply and strategy SZ.

However the quantity of the PurRqs generated 1 month in advance is not exact from the PIR since we have months with 28 days, 30 days and 31 days. Is there a setting we can achieve this? The PurRqs quantity should be exact quantity from the PIR and should be created 1 month in advance.

Please see the the illustration from the link below.

http://www.multiupload.com/M5GY5JVAE9

Thanks a lot in advance,

Marcus

Former Member
0 Kudos

Hi Marcus,

In order to address the different number of days in different months, you have to define the 'fiscal year variant' accordingly.

Regards

Manotosh

Former Member
0 Kudos

Hello Manotosh,

Can you please detail how to set this?

Currently we define it in Product Master /SAPAPO/MAT1 > Lot Size Tab > Quantity and Date Determination Tab > Safety Days Supply = 31

Thanks in advance,

Marcus