SKF for Progress Analysis

Former Member
0 Kudos

Hi,

I have successfully run progress analysis using Estimate method . As my understanding after I run CNE1, system will record POC that I maintained in Estimate table into SKF. Which report I can use to see this SKF value ?

I have checked all SKF report in PS and even in Cost Center Accounting, but the report has no data.

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

Hi,

Execute 12EVA1 and 12EVA2 in CJE0.

Tnx.

Abdul

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Did you check the report CNE5???

Once you run CNE1 accordingly reports on CNE5 will update.

Regards,

SL