Hello Gurus,
SAP PS standard reports like POC, S_ALR_873013531 are fetching PR+PO value in planned cost. How can we restrict it to get only PO value
Srinag
Hope you are using network cost planning.
if you convert the PR to PO then system will consider only one value not both. may be you are creating PO manually.
Please check your valuation variant options whether it can be set as required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Srinag,
As per my understanding of your problem, report is S_ALR_87013531 where plancost shows sum of PR and PO. Now if you want PR and PO value seperately use report S_ALR_87013558 where values are comming in RenOrdPlan(Remaining Planning)
Commitment (PR+PO) and actual. etc now if you want to PR and PO commitment seperately then use report CJI5.
I think this will help you little bit
Regards,
Nilesh