Upgrade 4.5b to ECC 6.0 EHP4

Former Member
0 Kudos

Hi

If we were to upgrade from R/3 4.5b to the current ECC/NW version on AS/400 (iSeries, etc) would it be correct to assume that we would need to upgrade to 4.6c. run CPC conversion then upgrade to ECC 6.0 EHP4?

Thanks in Advance

Matt Milne

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

They would probably want to include the Unicode conversion in there as well.

Thanks Volker

Former Member
0 Kudos

Hi Matt,

that request to end up in unciode makes our further ideas even more efficient ...

Regards

Volker Gueldenpfennig, consolut international ag

http://www.consolut.com http://www.4soi.de http://www.easymarketplace.de

Former Member
0 Kudos

Hi Matt,

unfortunately, yes ;-(

You remember the UABC92 class for the EBCDIC->ASCII CPC in Foster City ... this is still be needed for 4.5B customers ...

=> upgrade to 4.6C EBCDIC

=> EBCDIC->ASCII CPC

=> Upgrade 4.6C to 6.04

as this is pretty ugly, we had a few customers calling in to optimize this process. If you are interested we could talk on a few options offline.

Regards

Volker Gueldenpfennig, consolut international ag