we are clearing Usage decision each & every lot for which taking lot of time, if any setting for a GR Document number/Multi GR document nos connected lots to be cleared at a time automitically,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can use functionality of Auto UD which you can have by customizing it in SPRO.

Also if it is just for the sake of clearing inspection lots then better reduce generation of inspection lots at first i.e. activate quality inspection wherever it is essentially and not merely just making a process of mechanically clearing inspection lots.

Hope this helps.

Regards,

Tejas

Former Member
0 Kudos

Thanks,

Give path for auto UD settings and what are the settings

Anupam1143
Active Contributor
0 Kudos

HI

Go to SPRO>QM>Quality Inspection>Inspection lot completion>plan automatic usage decision>select your plant> imspection lot completion> auomatic Usage decision

Regards

Anupam Sharma

Former Member
0 Kudos

Hi,

In addition to Anupam's reply,

Follow the SPRO path for Auto UD---> Select your plant for AUTO UD settings -


> then go to InspLot completion tab where you need to define following time fields under Automatic Usage Decision tab page :

Delay time for skip lot (in Mins)

Waiting time (hrs) & Waiting time (Mins).

Waiting time is the time which must elapse after inspection lot creation after that only system will carry out automatic usage decision.

Save above settings.

Further as a master data part, you need to maintain tick in Automatic UD check box for the respective material for which you want activate automatic UD.

Hope this clears your doubt.