Hi Folks,

I need to bring up corresponding R/3 vendor number in the search when user tries to create a SC, and also print the SAP vendor no on the PO. Can you kindly advise how i need to proceed with this?

Akshay

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Akshay,

You will get the SAP R/3 vendor number from the table VENMAP for the corresponding BP number at SRM. So You will basically need to do a select for the same in order to retrieve this data.

Regards,

Sapna

ricardo_cavedini
Active Contributor
0 Kudos

Hello,

Do you have different number ranges in ECC and SRM? Usually, bp vendor number in ECC corresponds to ECC vendor number.

Regards,