on 04-21-2011 12:20 PM
Dear Experts,
materials are purchased against reservation.
GRN GI has been done even activity is confirmed 100% but
in reports there is no cost showing for materials..
when i take call up for the WBS, material wise cost is there..
Report s_alr_87013558.
what to do..?
s_alr_87013558 is budget report , are you expecting costs there?
Try CJI3 or s_alr_87013532 instead.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Material Procurement process is different & the concept of Reservations is different.
There is no concept like purchasing with & without reservation.
In PS you have an option of generating the PR & Reservation at the same time for a material component (particularly if you are dealing with Project Stock).
Create a statistical Cost Element for your stock GL account as suggested in earlier threads.
Once you make GR against your PO, then your CJI3 report will show all the line item costs. Each line item will show you the value / cost element / material number / quantity / material document number & many more as per your requirement.
Use ALV report options like filters etc... to arrive at your sigma / sub sigma values as required.
regards
thank you Krisap.
can you please comment on the following.
For an activity Material Components and Service component are assigned.
in report,
For Services Actual cost is displayed as that of PO value.
But for material no value.
in call up report when i apply filter for cost element cement consumed and then sub sigma
System shows 5 line items under Cement Cost element and total of it.
this total is actual cost for material cement and should be displayed as of services are displayed.
if this happens my problem is solved.
following are the detailed steps.
eg. Activity is PCC
Report s_alr_87013558
when I run report
actual cost
wbse RCC xxxx
WBSE BASEMENT RCC xxxx
NWA PCC 60142
CMP Cement 0.00
CMP Sand 0.00
CMP Fly ash 0.00
NWA Service 8955
Cost Element names
Cement Consumed
Sand Consumed
other raw material consumed (for fly ash)
Services consumed
when i take call up report for cost 60142
line items for cement sand fly ash and services are displayed.
in filter subtotals are like
cement 20151(7 LI)
sand 30027(10 LI)
fly ash 1008 (4 LI)
service 8955 (single line item)
these costs are against withdrawal qnty.
the text you mentioned under 87013558 report details :
CMP Cement 0.00
CMP Sand 0.00
CMP Fly ash 0.00
this seems to be the description of your network activities.. right? If so, then cross check the account assignment in your material PO. It might be some other project object.
where as your Cost Element reports are showing the correct value in the other report as you mentioned.
regards
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.