VPRS is not getting copied sometime to the target document.

Former Member
0 Kudos

Hi,

While creating Credit Memo Request with reference to Invoice, sometimes VPRS Condition Type is not copied from Invoice to Credit Memo Request.

But, when Debit memo Request is created , VPRS is getting copied always from Invoice to Debit Memo Request.

I have checked the Item Category, Copy Control as well as Pricing date in the target document (Cr memo Req). All those are fine.

I am not able to find out the reason why sometimes the VPRS Condition type is not geting copied.

Can anybody help me on this what can be the possible reason for it ?

Edited by: pradyumna on Apr 20, 2011 5:53 PM

Accepted Solutions (0)

Answers (3)

Answers (3)

Lakshmipathi
Active Contributor
0 Kudos

In Credit Memo Request, what was the message system was giving for VPRS, once you click the Analysis button ??

thanks

G. Lakshmipathi

Shiva_Ram
Active Contributor
0 Kudos

Check whether any routine assigned in the requirements column for this condition type in the pricing procedure is causing this issue.

Regards,

Former Member
0 Kudos

Hi,

Please check if the field 'Determine cost' is checked at Item category level.

Regards,

Peeyoosh.