Hi,
We are on PPM5.0.
Coding masks in PS restric us to use the Project and Phase IDs (in cProjects) according to the PS naming convention.
Having named the phase ID in accordance to the PS level 2 ID, when I "Flag for transfer", I get accounting errors in the cockpit. Acordingly the Phase WBS element is not created.
Even when I have named the phase ID as ABC.123 (for e,g,), the cockpit still gives the error with the standard Phase ID.
It says, WBS element with ID 1900000.....2011 could not be created.
What could be wrong?
Thanks.
Issue resolved. The problem was mandatory fields marked in the PS Profile. We relaxed these fields and were able to resolve the issue.