Hi,

Can anybody please explain me the meaning of following settings in DMR

Stage 100

Inspection Severity - 4

Initial Inspection Stage - Checked

Stc-Stage Changed -Checked

No Of Insp - 1

New Stage -200

Rejections -1

New Insp Stage -100

Stage-200

Skip - Checked

Stc-Stage Changed -Checked

No Of Insp - 32727

New Stage -200

Rejections -1

New Insp Stage -200

Thanks

Diwakar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

1.what exactly this means is

1.If first lot is accepted/UD taken then Inspection will move to next stage which is skip.

2.If fiest lot is rejected then it will remain in same stage.

3.Now in second stage which is "skip " you will carry out No Of Insp - 32727

4.If any one lot rejected still it will remain in same stage as next stage is not first one but it is 200 which is always skip.

In short after decision of your first lot system will only flow in second stage irrespective of rejectionn/acceptence of lot.