on 04-19-2011 5:14 AM
Hi All,
I am creating a handling unit via HU02. The status is 'Planned' and is an unassigned handling unit. After that, whenever I tried to assign this HU to my shipment, it always prompts me this error 'HU is assigned to an object that cannot be processed here'. I do know where went wrong as it is unassigned HU but still unable to assign it to my shipment. I have activated batch management in this scenario as well and thus I am packing the material by batches into the HU.
Appreciate any advice and solutions on this.
Thank you!
Regards,
Yvonne
Hi,
Create HU with stauts In the Warehouse and then assing HU to shipment.
Hope this helps you..
Rgds,
Kris.