on 04-18-2011 1:38 PM
Dear Experts,
My case is as following.
1.I Define amount of work 1 M3 in an activity in CJ20N
2.I confirmed 2 M3 of work, and it executed correctly.
3.I changed amount of work to 5 M3.
Remaining work should be 3, But its showing Zero in CN47N
Kindly suggest
Regards
HI,
What is the "remaining work" shown in CN41N ? That should be equal to 3 M3.
CN47N is a list of already made confirmations & here your sequence of actions need to be considered. as of now (as you have already changed the amount of work to 5 M3) cancel your previous confirmation, re confirm & then check the report.
regards