cancel
Showing results for 
Search instead for 
Did you mean: 

Remaining Work not showing Correctly in CN47N

ashutosh_saraf
Participant
0 Kudos

Dear Experts,

My case is as following.

1.I Define amount of work 1 M3 in an activity in CJ20N

2.I confirmed 2 M3 of work, and it executed correctly.

3.I changed amount of work to 5 M3.

Remaining work should be 3, But its showing Zero in CN47N

Kindly suggest

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

What is the "remaining work" shown in CN41N ? That should be equal to 3 M3.

CN47N is a list of already made confirmations & here your sequence of actions need to be considered. as of now (as you have already changed the amount of work to 5 M3) cancel your previous confirmation, re confirm & then check the report.

regards