on 04-18-2011 6:00 AM
Dear Friends,
We are having few work centers in quality department where we use this work centers for quality inspection.
Now i need to capture the cost incurred during the inspection process. In inspection plan can i have more than one work centre
in operationa field. i referred few threads where we can generate QM-order for this. Please let me know how to carry out this
process.
Thanks in Advance.
Edited by: dayanan on Apr 18, 2011 7:00 AM
Thank you very much.
Issue is closed
Edited by: dayanan on Apr 18, 2011 1:38 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sujith,
I followed the same steps as mentioned in the above thread. i can see the QM order generated in material master.
But , at the time of result recording and saving i am not getting any POP-up where i can enter the actual time incurred for an
particular operation. Please let me know , where i have to check to get the pop-up at the time of results recording.
And also let me know in inspection plan , which control key i have to use. The same control key which i will be using to create
Work center for quality.( PI01 OR QM01)
Edited by: dayanan on Apr 18, 2011 8:18 AM