04-16-2011 6:08 PM
Hi,
I have a doubt on Return Processes in Allocation.
Process:
- Allocation Table created
- WA08 (Follow on doc created) PO & STO
- WF10 Collective PO
- PGR in DC --> Distributes to store
The above is the Procurement Process.
Now the question is -
What are the Different Return Processes from Store to Vendor???
Thanks,
Kallol.
04-18-2011 12:19 AM
Hi,
There can be two process that come to my mind, there can be others depending on business need.
1. Return PO from Store to Vendor.
2. Return Allocation --> Return STO --> GR in DC --> Return PO to Vendor --> GI from DC
Cheers
Barry
04-18-2011 12:19 AM
Hi,
There can be two process that come to my mind, there can be others depending on business need.
1. Return PO from Store to Vendor.
2. Return Allocation --> Return STO --> GR in DC --> Return PO to Vendor --> GI from DC
Cheers