Experts,
We are wanting to use some custom logic at the time the system executes Cap Reqt calculation & later the Cap availability checks. We are dealing with regular Time-continuous resources which are planned as Finite.
Want to know of a BAdi that I could use in that area. Has anyone used enhancement for Cap Req or Cap avlbl chks?
Thanks
Hi Andy,
Please try with the below BAdis available for capacity planning.
/SAPAPO/SNP_CAP
/SAPAPO/CRES_CAPAPROFILE Capacity profile
/SAPAPO/CRES_DEFS Resource Definitions
/SAPAPO/CRESCIF CIF Transfer Resources
/SAPAPO/CRESDOWNTIME Semantik for Downtime
/SAPAPO/CRESEDITQUAN /SAPAPO/CRESEDITQUAN
/SAPAPO/CRESPPBUCKET Change the PP/DS Bucket
Regards,
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Saurabh,
I'm looking for a BAdi/method within the Planned Order creation mode (RRP_SRC_EXIT) that would enable me to re-calculate the Cap Requirements. Any planned order needs the following for completing -
1. PDS explosion (determines the components & the machine/source)
2. Numbers of hours required (Capacity Requirements)
3. Capacity avlbty check (Compare Cap Req with available Cap)
I'm looking to modify the Cap Reqt @ the time of creation of the Planned Order & then trigger Cap Avlbty check based on the newly calculated Cap Req
Any help would be a big plus for me
Cheers