andy_yeri
Contributor
0 Kudos

Experts,

We are wanting to use some custom logic at the time the system executes Cap Reqt calculation & later the Cap availability checks. We are dealing with regular Time-continuous resources which are planned as Finite.

Want to know of a BAdi that I could use in that area. Has anyone used enhancement for Cap Req or Cap avlbl chks?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Andy,

Please try with the below BAdis available for capacity planning.

/SAPAPO/SNP_CAP

/SAPAPO/CRES_CAPAPROFILE Capacity profile

/SAPAPO/CRES_DEFS Resource Definitions

/SAPAPO/CRESCIF CIF Transfer Resources

/SAPAPO/CRESDOWNTIME Semantik for Downtime

/SAPAPO/CRESEDITQUAN /SAPAPO/CRESEDITQUAN

/SAPAPO/CRESPPBUCKET Change the PP/DS Bucket

Regards,

Saurabh

andy_yeri
Contributor
0 Kudos

Hi Saurabh,

I'm looking for a BAdi/method within the Planned Order creation mode (RRP_SRC_EXIT) that would enable me to re-calculate the Cap Requirements. Any planned order needs the following for completing -

1. PDS explosion (determines the components & the machine/source)

2. Numbers of hours required (Capacity Requirements)

3. Capacity avlbty check (Compare Cap Req with available Cap)

I'm looking to modify the Cap Reqt @ the time of creation of the Planned Order & then trigger Cap Avlbty check based on the newly calculated Cap Req

Any help would be a big plus for me

Cheers