on 04-14-2011 12:13 PM
Hi,
i would like to know if it is possible to write a dependency for a specific operation in a standard network in order to change "invoice percentage" for a specific milestone depending on the value of a specific characteristic.
If it is possible, how should i proceed?
Thanks in advance.
Luis.
Hi,
My First response would be "Not Possible".
It may be possible that a dependency triggers a user field value change in the activity itself & then while saving the project, an exit comes into picture (if an exit for this exists) which changes the respective milestone invoice % .
But in this also, if you have more than one milestone for the activity, then it is doubtful.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.