Hi,

i would like to know if it is possible to write a dependency for a specific operation in a standard network in order to change "invoice percentage" for a specific milestone depending on the value of a specific characteristic.

If it is possible, how should i proceed?

Thanks in advance.

Luis.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

My First response would be "Not Possible".

It may be possible that a dependency triggers a user field value change in the activity itself & then while saving the project, an exit comes into picture (if an exit for this exists) which changes the respective milestone invoice % .

But in this also, if you have more than one milestone for the activity, then it is doubtful.

regards