cancel
Showing results for 
Search instead for 
Did you mean: 

How to get Phases linked to a decision point at run time?

former_member31961
Contributor
0 Kudos

Hi All,

I need to get the phases linked to decision point at run time, i.e on save of the item/Project. I have used the FM DFM_RETRIEVE_ASSIGNED_OBJECTS

This gives the values which are already saved. But i need some FM/Class which will give values at run time.

Any response would be hignly appreciated.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

mariano_sabiche
Active Participant
0 Kudos

Shrinivas;

To link Decision Point's to Project Phase's, first of all, you have to configure the DFM.

Are you in version PPM 5.0?

See this thread -->

Best regards.

Mariano