Planned cost in cProject - PS integration

Former Member
0 Kudos

Hi,

We were integrating cProjects with ECC, and planning cost in cProjects against projects. When we push the cost to project system (through accounting integration) and run the Ad Hoc Cost Estimate via transaction CKECPCP, we were getting an error stating Cost element XXXXXX is not assigned to a cost component. I fixed this error by assigning cost component to cost element in transaction OKTZ.

My question is, why is system is expecting for a cost element assignment to a cost component even for planned cost? I expect to see this error for actual cost, but why this is happening even for planned cost. Appreciate your input.

Aman

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

check okkt , under Misc tab check for the restriction.

Former Member
0 Kudos

Thanks. I actually checked IKKZ, as we use Ad Hoc Cost Estimates. In the Misc tab, it's blank. Looks like there is no restriction.

Former Member
0 Kudos

Not quite sure, but you are planning against version 0 ( active version) which would need and assignment to cost element , isn't?