on 04-13-2011 10:44 AM
Hi, Gurus!
Could you explain me about activation PPM (tran. /SAPAPO/SCC03)?
Use of a Plan is "P"
For what it is necessary?
When I have executed activation PPM, APO have displayed the messages:
"You cannot use unit for bucket consumption of res. XXX"
"Assign a value to at least one bucket consumption"
Hi,
Request you to check for the resource whether variable bucket consumption and unit has been maintained in the corresponding mode of the operation in PPDS PPM.
If not maintain the variable bucket consumption and unit and then activate the PPDS PPM.
Thanks,
nandha