Hi masters of SRM
Into SUS client the vendor make Confirmation of New PO the status is confirmed.
problem.
the message PurchaseOrderConfirmation_out ist send to SRM EB with status sucessfully
no message error is found neither SRM/SUS or SRM/EBP in sxmb_moni transaction but in bbp_pd transaction on ebp client no found for bus2232.
any confiuration is required ?
Thanks a lot .
Edited by: Oscar vazquez on Apr 12, 2011 11:30 PM
you need to check in the transaction 'BBP_PD' in the purchasing system ( SRM ) with object_type equal to 'BUS2209'. and also check in the Purchase order --> tracking tab which will show all the documents linked to the PO
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Oscar,
For more information on the SAP Solution Manager content, see SAP Note 1230438 and the SAP SRM
Master Guide at http://service.sap.com/instguides under Installation & Upgrade Guides SAP
Business Suite Applications SAP SRM SAP SRM Server 7.0
SAP Supplier Relationship Management 7.0: Service Procurement
Classic
check if the Document Type is configured.
check the Number Range:
SRM Server - Cross-Application Basic Settings - Number Ranges - Supplier Self-Services Number Ranges - Define Number Ranges for Confirmations
Check the IDOC configuration:
PurchaseOrderConfirmation_Out
ORDRSP.ORDERS02
Rgs,
Pedro Marques - SRM Solution
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.