there is no stock is available in ATP but all orders placed with perticaular material are confirmed for customer requested delivery date.

kindly reply.

thanks

in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

So what's your issue?

Former Member
0 Kudos

my question is if there is no material then how can the system confirm the delivery date.

in co09, mdo4,availbility it is showing 0 quantity. its a 3 rd party order.

its an SAP 3.1

kindly suggest

Former Member
0 Kudos

How come 3rd party orders will have ATP?? please check schedule line cat CS not marked for Requirements/Allocation.

Hence system will confirms delivery date, and PR will generate, with reference to PR, business will raise PO > MIGO or MIRO.

We don't require ATP for 3rd party orders as vendor will deliver the goods to customer.

Hope its clear.

Answers (1)

Answers (1)

Former Member
0 Kudos

I think the scheduline line catergoy is not marked for ATP in customizing, please check, if you try to create delivery system will not allow to create, try and le us know.