Dear All,

when I want to make a PRT availability check for "Production Resources/Tools" in MD04. When I start it I get the following error:

-


PRT availability could not be checked

Message no. CO285

Diagnosis

The availability of the PRTs (production resources and tools) could not be checked for one of the following reasons:

There are no control parameters defined in Customizing for this plant and order type.

The control parameters defined in Customizing do not permit availability checks.

There is no checking rule defined for this plant and order type.

Procedure

Go into Customizing and check the corresponding control parameters for checking the availability of PRTs.

-


On the material master the setting for availability check is defined. For all other materials it works but not for "Production Resources/Tools"

Can you please help me with that. Which setting is missing?

Thank you very much.

Best regards,

Markus

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You need to define

1. Checking group

2. Checking rule

3. Scope of check

4. Checking control

In defining the checking control you need to define availability check for the PRT is required or not.

This has to defined for each order type/plant combination.

Also you need to define whether you want PRT availability check to be carried out during order creation or during order release.

Assign the scope of check in the Material master MRP 3 view.

Thanks,

nandha