Issue in releasing SPAU adjustment request

Former Member
0 Kudos

Hi All,

We have applied ST-A/PI Add-On in our ERP development system.

While doing it we encountered SPAU issue. Hence we did the modification

adjustment and recorded the changes in a transport request.As per SAP

help this request should be marked as adjustment transport so that it

can be imported in the follow up systems instead of doing manual

adjustments there.

( http://help.sap.com/saphelp_nw04s/helpdata/en/53/5c36c25db111d2b414006094b9ea64/content.htm )

To be marked as an adjustment transport this request should be assigned

to the predefined CTS project SAP_ADJUST. we have implemented CHARM for

change management and the project SAP_ADJUST is not available in our

landscape.

So please advise how to proceed in this regard.

Thanks,

Tapan

Accepted Solutions (0)

Answers (1)

Answers (1)

tomas_black
Employee
Employee
0 Kudos

Hello Tapan,

please check the attributes of SAP_CTS_PROJECT (in SE03) if the options related to "mandatory for all clients" and "specific for client XXX" are set. If so, please unselect them, this should make this project available.

Best regards,

Tomas Black