Tracking changes to an inspection plan

mike_mitchell
Explorer
0 Kudos

We need to know when an inspection plan has been created or changed, so we can distribute these changes via an idoc to an external system. QP60 shows the 'Task List Changes' and QP61 shows the time stamp and tcode of the change, so obviously these changes are being stored. Instead of a report though, we would like to trigger a workflow event soon after the specific inspection plan has changed.

We are on version ECC 6.0, and when changing an inspection plan with QP02, I see there is a menu path under 'Extras' for QP02 for 'trigger point parameter', but it is grayed out.

In the past, we have set up change pointers to monitor changes to master data of materials. We have also used trigger points on a routing to raise a workflow when a production order is dispatched.

Is anyone aware of how to set up either change pointers or a trigger point (or some other methodology) to track changes for an inspection plan?

Thanks - Mike

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can use Engineering Change Management to track changes for the Inspection Plan.

Regards

Ramakanth

mike_mitchell
Explorer
0 Kudos

As luck would have it, I found that the tables holding the changes were already being populated with the inspection plan records. Field CDPOS-TABKEY holds the material specific detail that can be extracted and used for comparison purposes.