on 04-11-2011 7:30 AM
Dear Guru,
Problem 1:
1. In the sales order, there are 3 lines items. As per there requirement each line item they want enter diffrent payment term.
for example
Material code Payment terms
1. Fixed z045
2. Variable z030
3. Pipes z015
how you can archive this goal. In customer master payment term is maintained only one. Please suggest me.
Problem 2:
1. Credit managment, If the credit block is there in the sales order(Due to credit limit exceed) order confirmation is no goes to customer.
how we can archive this goal by using the standard functionality.
Hi,
1. You can achieve it through manual entries
If you have 3 line item then at item level >> Billing document maintain payment terms
2. If credit limit exceed then confirmation should not go to customer
Can you tell me currently how you sending confirmation to customers
If it is through simple mail then go to
IMG >> SD >> Basic functions >> Output control >> Output determination using condition techniques >> maintain out put determination for sales document >> maintain out put determination procedure
Select procedure V10000 >> go to control data
for condition type MAIL maintain requirement 9/11
(If this is not work then create new routine and add your logic that if credit limit exceeds then do not(trigger) send confirmation)
kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
9 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.