Hi SAP Experts,
In my company we have a requirement to produce the same finish material in two work centers, using different BOM. This was achieved through production versions for production orders. Now we need to plan (Indipendent requirement & Plan orders )the material based on these two BOM.
We enter the indipendent requirement in MD61. I have given the production version against the requirement (In schedule lines tab). However i am unable to give two different requirements for the same day in different production versions.
Then i tried using different planning versions and assigning the different production versions to different plan versions.
Although my indipendent requirements are taken in different production versions(As I can see in MD04). When i run MRP plan orders are raised as the total of the requirements and in only one production version.
Please, Can some one help me to find a method to raise different plan orders for the same day in different production versions???
regards,
Madhushika
Dear Madhu,
Please check which production version is active in MD63.
regards,
Praz
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check what is the Availability Check that is maintained in the Material Master MRP3 view. It should be individual requirement.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.