Missing Planned Orders

Former Member
0 Kudos

R/3 4.7 - Long term planning

MS01 is not creating planned orders as I would expect for approx one-hundred materials (of thousands). -- Plant level

But when I run MS02 -- Material level, then planned orders are created.

I need this to work at the plant level. MS01 and MSBT (nightly batch job).

Thank you for solutions!

Best regards,

Jim

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Jim,

Check for planning file entry.

Best Regards,

DB49