on 04-07-2011 5:34 PM
Is it possible to have different types of components on a single work order? By this I mean to be able to put a stock, non-stock, and services in a single work order?
Hi
yes you can put the different type of material along with service in single work order
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for the responses
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It is very much possible to plan Non-Stock & stok items & also services in a single work order. Even you can plan stock & non-stock items for a single operation also by providing Item categories L: Stock Item & N: Non- Stock item.
Yatharth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.