Reg:: In-Process inspection ( Inspection type 03)

former_member184571
Participant
0 Kudos

Dear Friends,

i am using inspection type 03 for in-process inspection type.

i my master recipe i have used control key PI01 and i have attached MIC in operation itself.

Now i have an issue regarding Results recording . Suppose in master recipe if i have defined 5 operations , and if material gets

rejected in first operation only. As this inspection type is stock irrelevant , after result recording do i need to do Usage decison.

if i want to re-process , how can i re-process the same operation ..?So that i can make cresults recording once again for the

same operation. And also please let me know which control key is suitable for in-process inspection type, to attach MIC'S in

operation itself.

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Inspection type 03 is not stock relevant, where as inspection type 04 (final inspection) is stock relevant.

You can explore inspection points in your case.

Standard Control key PP04 or PI02 is to be used for making MIC assignment mandatory.

Regards

Answers (2)

Answers (2)

former_member184571
Participant
0 Kudos

Thank u..

Former Member
0 Kudos

Hi ,

Since you already done UD , why dont you cancel the UD again ?

TQ.