on 04-06-2011 2:49 PM
Hello,
We currently use SLFN with 1 maintenance cycle, for 4 productive systems.
We want to close this maintenance cycle, and create 1 maintenance project/cycle for each production system.
Is it possible to transfer the SLFNs that are still opened after the 1st one is closed, to the 4 new cycles?
I could only find that SLFNs are automatically reassigned to a new maintenance cycle on the same project they were created on.
Thanks.
Hello,
I think that a split is not possible - but I may be wrong.
There is a workaround for all open corrections with transport requests and transport tasks, which have not been released:
You're able to create new corrections via ChaRM and reorganise the transport tasks: they can be assigned to other transport requests. After reorganisation, the ("empty") corrections, which were created before, can be rejected.
(It doesn't work for released transport tasks.)
Best regards
Horst
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your answer. I did not have that much hope, but what I have read confirms it.
I will leave this thread open in case someone has managed to do it anyway.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.