Budget Exceed Error - Cutback Process

Former Member
0 Kudos

Hi All,

We are on ECC 6.0 (EhP4) with PSM and Joint Venture Accounting (JVA) modules implemented.

While executing JVA Cutback Process using transaction code (GJCB) system generates budget exceeded error. We do not maintain budget for Cutback G/L Account because usually only Credit entries are made against this particular G/L.

Kindly share your input.

Regards,

Hanif

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Hi, how did you exclude accounts?Via Derivation Strategy for Tolerance Profiles?If so then check it.

View solution in original post

4 REPLIES 4

Former Member
0 Kudos

Hi, how did you exclude accounts?Via Derivation Strategy for Tolerance Profiles?If so then check it.

0 Kudos

Hi Alex,

Yes, we can exclude accounts using Tolerance Profile.

But I am worried JVA Cutback is a standard process which only transfers all expenses to a particular account say "Cutback Expense Account" at period end. So I thought that such account should be budget expemted by default.

Well, your answer is appreciated.

Regards,

Hanif

0 Kudos

Hi,there is no extemption by default. you need do it yourself

0 Kudos

Hi,

Could you please provide me with the message id and no. for the error.

I can than have a look at the system and tell you how and why the error is triggered.

Regards,

Satyajit