Hi Experts,
We have implemented Funds Management for cost center budget checking and everything is fine so far.
However, recently we have identified that system does not check budget when WBS cost is settled to a cost center. This is Actual Settlement, whereby cost is transferred from WBS to cost center. We want system to restrict such settlements unless budget is available on cost center.
Regards,
Hanif
04-06-2011 1:23 AM
Hi Hanif, the online documentation for Integration with Cost and Project Controlling, clarifies your issue
"....Periodic postings that result from programs such as assessment or settlement are only assigned values; however, no check is carried out by the active availability control. This means that these postings will be permitted even if sufficient budget is not available. You must use manual budget transfers to correct any budget deficits that result. To display the budget deficits, you can run the program to Display Budget Deficits for Expenditures in the Annual Budget (RFFMAV03X). "
http://help.sap.com/erp2005_ehp_04/helpdata/en/f0/ca5716260211d28a430000e829fbbd/frameset.htm
Regards
Cesar
04-04-2011 12:14 PM
Hi, you need to activate CO-FM integration, IMG-PSM-Funds Management Government--Integration/Update-Integration-integration of Cost and Project Controlling with Funds Management
04-04-2011 1:23 PM
Hi Alex,
Thanks a lot for the input. I made integration configuration for "All Transactions" and activated the "Co-FM" integration but behaviour of system remains same. I am still able to settle cost from WBS to Cost Center.
It seems that these settings only provide budget check for internal cost transfer activities of CO module only. It does not have any affect on cost of WBS which is settled from PS to CO module.
Any other thoughts or am I making some wrong settings?
Regards,
Hanif
04-04-2011 1:35 PM
Hi. Should work.
Check FM doc, generated during settlement, is it ok? I mean it'd to trigger error message for budget?
Also reconstruct AVC with FMAVCR01.
Hope you set check box Budget assigned in table V_FMCOVR
04-04-2011 1:54 PM
Hi,
Please, verify the data flow of this settltment document in terms of FM addresses. The point is that there is no budget on the cost centre, as you mentioned it, but rather on the relevant FM object that is derived based on this info. So, make sure that the FM document created is assigned to the relvant FM address.
Regards,
Eli
04-05-2011 7:13 AM
Hi Alex,
Thanks for your support. I have noted the following things:
1. Check FM Doc - no trigger for error message
2. Reconstructed AVC using FMBV (since we are using Former Budgeting) - still no affect
3. Budget Assigned check in table V_FMCOVR is also SET
It still allows settelment without error although it picks up correct FM Objects for whihc AVC is ON. When I try to post directly using FB50 it does give budget exceed error message.
You are right that these setting should work but I am unable to figure the reason for no budget check. please assist.
Regards,
Hanif
04-05-2011 7:15 AM
@ Eli:
Yes, the budget is checked on relevant FM object which is picked by system as maintianed in FMDERIVE. I have double checked that there is ZERO budget on funds center it should give error message like it is giving while posting directly thru FB50.
Regards,
Hanif
04-05-2011 8:41 AM
Hi.
Check if Activity groups 50 assigned to you FM ares/Budget profile in OF20.
04-05-2011 8:56 AM
Yes, I have assigned ++ (All Activity Groups) agianst Budget Profile.
Regards,
Hanif
04-05-2011 9:07 AM
04-05-2011 6:08 PM
Is your WBS settlement cost element a 30/3 commitment item? If your internal order settlement behaves fine in AVC, change WBS settlement rule to use the same settlement CE and see what happens.
Also check your sender funds center and recever funds center. If they are the same or they belong to the same AVC control object, then there will be no message.
04-06-2011 1:23 AM
Hi Hanif, the online documentation for Integration with Cost and Project Controlling, clarifies your issue
"....Periodic postings that result from programs such as assessment or settlement are only assigned values; however, no check is carried out by the active availability control. This means that these postings will be permitted even if sufficient budget is not available. You must use manual budget transfers to correct any budget deficits that result. To display the budget deficits, you can run the program to Display Budget Deficits for Expenditures in the Annual Budget (RFFMAV03X). "
http://help.sap.com/erp2005_ehp_04/helpdata/en/f0/ca5716260211d28a430000e829fbbd/frameset.htm
Regards
Cesar
04-06-2011 5:28 AM
Hi Minghong,
Thanks alot for your assistance, in fact all point that you identified are OK.
Regards,
Hanif
04-06-2011 5:35 AM
Hi Cesar,
Thanks you for the very appropriate answer and identifying the relevant SAP source documentation.
Although, this shows inconsistency in system's behavior as I am unable to grasp the logic behind this. After all active contols in place, manual entires to corret budget deficits seems a joke... anyways this is SAP fact... so ENJOY SAP
Again, thanks alot for your support.
Regards,
Hanif
03-20-2013 2:56 PM
Hi, Muhammad!
Kindly let me know - have you solved your issue with FM AVC for WBS-element Settlement?
I'm facing the same problem now. Would like to have a suitable solution.
Regards,
Oleg Tolstashov