on 03-31-2011 6:16 PM
Hello EWM gurus
We run our logistics operations in 4.6 C with Distribution view from IBM as WMS at all our PDCs. PDCs are setup as plants in R/3.
We want to try EWM in one of our new PDCs.
Is it possible to configure our R/3 to connect to EWM for the new PDC only , where as other PDCs would continue to operate in Dview with idoc interfaces?
If yes , please let me know the settings required.
Thanks a lot for your help.
Hi,
If each PDC is defined as a new plant, then these are the Steps:
1. Assign Plant /Storage Loc to Warehouse in ECC
2. Activate the Warehouse in ECC for EWM . Here is the Menu Path:
Logistics Excecution->Extended Warehouse Management Integration->Basic Setup of EWM Connectivity->Maintain Extended WM-Specific Parameters and activate your warehouse for EWM.
Hope that helps
Thanks
Vinod Madhanu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.