Not getting detail of Assigned value

ashutosh_saraf
Participant
0 Kudos

Dear Experts ,

I am not getting detail of Assigned value in S_ALR_87013542 & S_ALR_87013558.

I have no commitment but its showing actual cost is 57.Kindly put some light on in.

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

in tcode cj31; Extras -> Availability Control -> Analysis, you will get the assigned value full details.

Regards,

Harsh.

Former Member
0 Kudos

Hiiii

Project Hierarchy Reports work well with configurations of value categories in customizing

Check for the creation of value categories in configuration using the transaction code OPI1 and check for consistency using the t.code CJVC.

Hope this helps....

Regards

Kaashif M

Answers (1)

Answers (1)

Former Member
0 Kudos

Assigned value is calculated from your "Commitment" & "Actual" values postings. You will not get any details in those reports. See the line items of your Commitments & Actuals individually.

You can analyze the contributors to your assigned value (line items with value types) in CJ31, availability control analysis.