ERROR: RFx Time always Changing after save edit

Former Member
0 Kudos

Hi Expert,

I'am using SRM 7 and ECC 6, and use extended classic scenario.

When I try to check the time after edit RFx (Submission Deadline,

Opening Date and Technical RFx Response Opening Date), its always change it self and different with our edit before.

I don't know why it washappen.

Need your response...

Thanks and Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Check if you have active implementation of BBP_DOC_CHANGE_BADI which changes the time fields for your RFx (check BBP_PD_BID method).

If there is no time specific logic in your BADI implementation mentioned above, you might need to apply some notes:

Note 1469471 - Submission deadline of RFx gets changed with Timezones (this one is for SRM 701, but I believe it also applies to SRM 7 release. You could create an OSS to SAP for them to extend the validity for this note.)

Note 1559880 - The RFx "End Date" is not displayed in the bidder time zone

Note 1573014 - Submission Deadline timezone of RFX converted to UTC

Note 1548529 - End date gets changed when follow on document is changed

Edited by: Jay Yang on Mar 31, 2011 6:42 AM

Former Member
0 Kudos

Hi Jay,

Thanks for your reply....

But i have problem with Technical RFx Response Opening Date.

Step-Step:

1. Open RFx number

2. Click edit in screen RFx

3. Input Submission Deadline (Date and Hour)

4. Input Opening Date (Date and Hour)

5. Input Technical RFx Response Opening Date (Date and Hour), ex: 02.04.2011 and 14:00:00

6. Save transaction

7. Hour in Tecnical RFx Response Opening Date Changes, ex: 02.04.2011 and 16:00:00

Can anybody help for this problem..

Thanks and Regards,

Former Member
0 Kudos

solved..

by setting time in server..

thx