Dear Experts,

what are the prerequisites steps to execute split confirmation, i am not able to do it for category 001 (Machine) or Category 002 (Person)

please feed me back in how to make split confirmation

Thanks & Regards

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thank you

Former Member
0 Kudos

I am facing the same problem and the SAP notes mentioned here are of little help. Were you able to solve it and if yes than please let me know how.

Thanks!

Regards,

Hashim Abbasi

Former Member
0 Kudos

Hello,

when i am going to make collective confirmation in CN27 i put number 1 in Spl field, system generate the following error

Individual capacity / 1 does not exist (check entry)

Message no. RU188

Thanks & Regards

Former Member
0 Kudos

Not sure but you can refer the notes 488097 & 532053 which may help you to procees further,

former_member201206
Active Contributor
0 Kudos

Hello Mohammad,

I am not sure, what the problem you exactly have. Generally the confirmation to split should be possible.

Please review the consulting note 543362, if you can get some helps. It describes mainly how the splitt confirmation affects the scheduleding afterwards, as the splitt confirmation itself is somehow straightforward.

Kind regards,