on 03-29-2011 8:03 PM
Hello,
I have have a system that's jobs are being monitored and reported by SolMan's central autoreactions with the R3BPServerSpecAbortedJobs MTE Class.
Every day at 10am we get a notice that a job failed, but that job in the system did not fail. The job in question does run at that time but is successful.
Is there a table holding on to something or is the autoreaction seeing something that thinks it failed?
Thanks for the suggestions.
Ryan
Another job was scheduled in table TBTCS. Deleted the job and the notifications stopped.